......@@ -129,14 +129,14 @@ The total budget for the CCS is 22 XMR which, with the price of 1 XMR today, tot
## The Timeline
For the moneroj.info site, as I'm not working full time on this, I expect to complete one milestone per month and a half. This would be a total of 4.5 months starting from December 1st 2021. I will add an extra month and a half for anything that could happen, so 6 months for the work on moneroj.info. This means moneroj.info should be ready and completed by April 2022 at most. The expected timeline is:
For the moneroj.info site, as I'm not working full time on this, I expect to complete one milestone per month and a half. This would be a total of 4.5 months starting from December 1st 2021. I will add an extra month and a half for anything that could happen, so 6 months for the work on moneroj.info. This means moneroj.info should be ready and completed by June 2022 at most. The expected timeline is:
- Milestone 01: January 15th, 2022
- Milestone 02: February 15th, 2022
- Milestone 03: March 15th, 2022
- Milestone 01: February 15th, 2022
- Milestone 02: April 15th, 2022
- Milestone 03: June 15th, 2022
An extra month and a half is added, so there is some margin for each of the deadlines if anything unexpected happens.
On the other hand, the maintenance work can be released all at once in 6 months from this proposal, or at the very beginning. I would propose for it to be paid at the end of the 6-month period, this being on May 31, 2022.
The deadline for this CCS is `May 31st, 2022`.
The deadline for this CCS is `June 31st, 2022`.